PACT Housekeeping Meetings
Thursday 19th November 2026
Dan from Build DPD joined us this week, and it was great to have such a pro give us his thoughts and help us steer the ship in the right direction. He dived straight in, giving us a great timeline to work on straight away that will give us a much better idea on costings, and give PACT the chance to pick and choose where they would like to focus the budget.
His proposed timeline that we are now working on is:
1. SKiNT will send him the drawings we have.
2. Dan will get a better idea of the lay of the land, and give us some rough ideas on costing, noting what features are the most expensive and giving us an overall estimation of the works, to the nearest £25k or so.
3. PACT will then work with these costings and prioritise where to spend the money.
4. Advanced costings, this is the point where we could include a QS.
Lucy also spoke with Collette (QS at SHU) which was a bit of a reality hit for us all, with concerns about GANTT charts, scope of works, bill of quantities etc. Dan Reassured us that while all of this is true, he doesn’t think these are relevant worries at this stage and that a lot of these points will be the responsibility of the main contractor, once appointed.
Overall it feels like great timing for Dan to get involved, and we are really excited for the momentum to pick up now that we have someone with experience guiding us with where to go.
Dan from Build DPD joined us this week, and it was great to have such a pro give us his thoughts and help us steer the ship in the right direction. He dived straight in, giving us a great timeline to work on straight away that will give us a much better idea on costings, and give PACT the chance to pick and choose where they would like to focus the budget.
His proposed timeline that we are now working on is:
1. SKiNT will send him the drawings we have.
2. Dan will get a better idea of the lay of the land, and give us some rough ideas on costing, noting what features are the most expensive and giving us an overall estimation of the works, to the nearest £25k or so.
3. PACT will then work with these costings and prioritise where to spend the money.
4. Advanced costings, this is the point where we could include a QS.
Lucy also spoke with Collette (QS at SHU) which was a bit of a reality hit for us all, with concerns about GANTT charts, scope of works, bill of quantities etc. Dan Reassured us that while all of this is true, he doesn’t think these are relevant worries at this stage and that a lot of these points will be the responsibility of the main contractor, once appointed.
Overall it feels like great timing for Dan to get involved, and we are really excited for the momentum to pick up now that we have someone with experience guiding us with where to go.
Decisions made:
Resources Shared:
Goals for next week:
- Final preparations for Open House